Quorn Park Solar Farm

Project Location:

Australia

Client Name:

Beon Energy Solutions

Project Description:

Our teams delivered surveying, pile distribution and pile installation works for the 98MW Quorn Park Solar Farm and associated 20MW Battery Energy Storage System (BESS).


The works provided the foundations required for tracker installation across the site and supported the successful delivery of the wider renewable energy development. Surveying, logistics coordination, pile distribution and installation activities were delivered to support efficient construction progress across the project.

Key Stats:

  • 98MW solar farm with 20MW BESS

  • NEXTracker Horizon system installed

  • 90,000 solar panels

  • Renewable energy generation for approximately 45,000 homes

5 Months

Duration

Challenge

  • Access to site significantly restricted during the early stages of the project due to road upgrade works

  • Limited vehicle movements and personnel permitted on site during mobilisation

  • Managing logistics, equipment deliveries and workforce access within allocated movement windows

  • Maintaining programme performance despite constraints

  • Coordinating site activities alongside ongoing infrastructure works

Solution

  • Developed detailed logistics and access plans to manage restricted site entry requirements

  • Coordinated vehicle movements through Beon's yard to maximise available access windows

  • Maintained strict communication and scheduling controls to manage personnel, plant and material movements

  • Optimised piling and distribution activities to maximise productivity during available working periods

  • Worked collaboratively with client and project stakeholders to minimise disruption and maintain programme certainty

Outcome

  • Surveying, pile distribution and installation works completed safely and efficiently

  • Access restrictions successfully managed without significant impact to programme delivery

  • Efficient logistics and access management enabled construction activities to progress despite early site restrictions

  • Supported the successful delivery of the 98MW solar farm and 20MW BESS development

  • Demonstrated our ability to overcome complex logistics challenges while maintaining schedule performance

  • Achieved one of the strongest schedule performances in the business, surpassing previous delivery records