Preseli Pumping Station

Project Location:

Ernesettle, Devon

Client Name:

Dŵr Cymru Welsh Water

Project Description:

OCU delivered the upgrade of pumping and control infrastructure at Preseli Clear Water Pumping Station, which supplies treated water directly into the distribution network.


The works included installation of a new duty/standby pumping arrangement, new MCC, and conversion of an existing building into a control room. Redundant equipment was removed and new control and feedback systems installed. All works were carried out on a live network, with temporary pumping and generator systems maintaining continuous supply.

Key Stats:

  • New duty/standby pumping arrangement installed

  • New MCC installed and commissioned

  • Temporary pumping and generators maintained supply 

  • Redundant pumps and control systems removed

2 Years

Duration

Challenge

  • Delivering pump replacement works on a live clear water network

  • Maintaining continuous supply using temporary pumping arrangements

  • Protecting water quality during staged testing and commissioning

  • Working within existing site constraints while upgrading critical assets

  • Ensuring system reliability while replacing key assets to new infrastructure

Solution

  • Developed detailed design and delivery planning prior to installation

  • Implemented a business continuity plan to maintain network supply

  • Installed temporary pumps and generators to support live operations

  • Applied double isolation procedures to ensure safe working conditions

  • Undertook staged offline testing prior to commissioning

  • Followed structured commissioning and chlorination procedures

  • Maintained regular coordination with Welsh Water operational teams

Outcome

  • New pumping system and MCC successfully installed and commissioned

  • Continuous supply maintained throughout the works with no disruption to the network

  • Water quality standards maintained during all testing and commissioning stages

  • Improved reliability and resilience of the clear water pumping station

  • Scheme delivered safely and in line with client requirements