top of page

Power Cable Replacements

Project Location:

Port Talbot, Wales

Client Name:

TATA Steel

Project Description:

OCU supplied and installed new power cables following a fire in the west basement at Tata Steel’s Port Talbot Hot Rolling Plant, which caused significant damage to existing assets.


The works included installing seven 3.3kV three-core cables and one 11kV three-core cable, each approximately 500m in length. Cables were routed from the 3.3kV descaling substation switchgear, through the pumphouse and along the scale crane gantry before terminating in the Dirty Water Return (DWR) drive room. The scope also included all associated containment, jointing, termination, testing and commissioning.

Key Stats:

  • 8 x 500m power cables installed

  • 3.3kV and 11kV cable systems

  • Full supply, installation, jointing and testing delivered

  • Works completed within a live industrial environment

3 Months

Duration

Challenge

  • Complex cable routing through existing cable basements and over the scale crane gantry

  • Restricted access requiring specialist scaffolding without disrupting production operations

  • Scale crane isolation required to allow safe access to the gantry

  • Challenging environmental conditions, including continuous flooding within the cable basement due to a damaged pipe

Solution

  • Undertook detailed cable route surveys to identify existing services, interfaces and support locations

  • Utilised existing penetrations and routes to minimise additional civils and reduce impact on live operations

  • Designed and installed bespoke scaffolding to provide safe access to the crane gantry

  • Planned works around agreed production windows, allowing temporary isolation and emptying of the scale pond without affecting overall output

Outcome

  • Critical Dirty Water Return power infrastructure successfully reinstated

  • Works delivered safely within a live production environment

  • High safety and environmental standards maintained throughout

  • Full project scope completed on time and within budget

bottom of page