top of page

Pen Y Ball Pipeline

Project Location:

North Wales

Client Name:

Dŵr Cymru Welsh Water

Project Description:

OCU delivered the construction of a 5.2km clean water pipeline between Lixwm and Pen Y Ball Reservoir in North Wales. The route included 4km along a busy B road and 1.2km across agricultural land.


The works involved installation of 450mm and 400mm PE pipeline, including butt fusion welding, valve installations, trunk road crossings and multiple live connections. A new pressure reducing valve (PRV) complex was also constructed.

Key Stats:

  • 5.2km clean water pipeline installed

  • 1600m of 450mm SDR11 pipe

  • 3600m of 400mm SDR17 pipe

  • 5 live connections completed

  • New PRV complex constructed

6 Months

Duration

Challenge

  • Delivering pipeline installation along a live B road with traffic management constraints 

  • Working through agricultural land with archaeological sensitivity including mine shafts

  • Managing difficult ground conditions including rock along the route

  • Coordinating multiple stakeholders including highways, landowners and environmental bodies

  • Maintaining safety across multiple work fronts and changing programme requirements

Solution

  • Installed pipeline using tracked excavation and controlled trenching methods

  • Undertook butt fusion welding using Trackstar system with certified joint testing

  • Implemented convoy traffic management system to control vehicle speeds safely

  • Coordinated works with Flintshire Highways through regular planning meetings

  • Installed stockproof fencing and managed easement corridor to control site access

  • Reused excavated materials for backfill to reduce environmental impact

Outcome

  • 5.2km clean water pipeline successfully installed and commissioned

  • Safe delivery achieved across live highway and rural environments

  • Effective stakeholder coordination maintained throughout the project

  • Environmental impact reduced through reuse of excavated materials

  • Scheme delivered in line with client specifications and programme requirements

bottom of page