Hawton 132kV Cable Diversions

Project Location:
Hawton, Nottingham
Client Name:
National Grid Electricity Distribution
Project Description:
OCU delivered the diversion of existing 132kV overhead line infrastructure at Hawton, Nottinghamshire, replacing eight spans of overhead line with a new underground cable system. The works formed part of a wider residential housing and relief road development scheme.
The project involved installing approximately 2.2km of new double-circuit 132kV underground cable between the existing network and a new terminal tower. Works included trench excavation, cable installation, jointing, telecoms duct diversion and commissioning, alongside the removal of overhead infrastructure.
Key Stats:
2.22km 132kV cable diversion
Double-circuit system - 6 × 1000mm² Cu XLPE cables
C.6 million litres of groundwater managed
New telecommunications duct route and chambers
Underground diversion enabling future housing and road infrastructure
5 Months
Duration
Challenge
Delivering the cable diversion within a live multi-contractor development environment
Managing significant groundwater ingress due to the high water table near the River Trent
Maintaining safe trench conditions while installing directly buried 132kV cables
Coordinating with multiple stakeholders including NGED, developers and local authorities
Adapting installation methods while joining the project during a later construction phase
Solution
Installed a 2.22km underground 132kV cable system in touching trefoil formation
Implemented controlled dewatering to maintain safe trench conditions
Managed approximately 6 million litres of groundwater
Adapted the installation from a direct buried system to a ducted solution for the final 800m to mitigate groundwater flooding risks
Installed new telecommunications duct infrastructure and chambers
Coordinated closely with the civil engineering contractor and other site teams to integrate works within the wider development programme
Delivered the scheme using OCU’s specialist high-voltage cable installation teams and calibrated pulling equipment
Outcome
Successful diversion of overhead infrastructure to a new underground double-circuit 132kV cable system
Enabled the removal of overhead lines and released land for residential and transport development
Groundwater challenges successfully managed without significant impact to programme
Improved long-term network resilience and reduced visual impact on the surrounding environment
Demonstrated OCU’s capability to deliver complex EHV infrastructure works within the NGED ED2 framework

