Grandstand Road Slip Lining

Project Location:

Grandstand Road, Herefordshire

Client Name:

Dŵr Cymru Welsh Water

Project Description:

OCU delivered a distribution mains renewal programme for Dŵr Cymru Welsh Water, installing 9.3 km of new mains following investigations into existing distribution assets. Works included renewal of ductile, cast and spun iron mains along Grandstand Road, a busy route bordered by residential and commercial properties and local points of interest.


While the wider scheme was completed predominantly via open-cut installation, the Grandstand Road section was better suited to a trenchless approach, reducing disruption and supporting safe, compliant delivery.

Key Stats:

  • 9.3 km of new mains delivered

  • Residential and commercial constraints managed

  • Traffic, access and ecology maintained; full regulatory compliance achieved

Duration

Challenge

  • Presence of asbestos cement required full compliance with HSE legislation and strict controls for safe handling and disposal

  • The densely populated location required clear and ongoing communication with residents affected by driveway access changes and temporary footpath diversions

  • Managing traffic on a busy main road was critical to maintaining safe access and programme delivery

  • A two-week shutdown over the Christmas period introduced additional programme constraints

  • Plant and equipment security was essential to prevent vandalism when left on site overnight

Solution

  • Pedestrian access was maintained throughout, with traffic management arrangements regularly reviewed and adapted as works progressed

  • Detailed traffic management plans were submitted to the client, providing clear arrangements for vehicle movements and minimising disruption to residents and local services

  • Plant and equipment were secured using Heras fencing where overnight storage was required

  • High standards of site cleanliness and housekeeping were maintained at all times

  • Residents were kept informed of planned works, with access reinstated as quickly as possible following each phase

Outcome

  • The scheme was successfully delivered with 9.3 km of new water mains installed, overcoming complex environmental, traffic and access constraints

  • Effective management of asbestos cement, unlined cast iron and ecological considerations ensured full regulatory compliance throughout the works

  • Trenchless construction methods minimised disruption to residents, businesses and the wider road network

  • All water main isolations were completed in full compliance with the New Roads and Street Works Act 1991

  • Cleaning, commissioning and handover were completed by OCU in line with client requirements, resulting in a reliable and future-proofed network