Aldoga Solar Farm

Project Location:
Queensland
Client Name:
Acciona
Project Description:
Our teams delivered the construction works for the 485MW Aldoga Solar Farm in Gladstone, Queensland.
The scope included surveying, pile distribution, drilling, pile installation, tracker and module installation, civil works, electrical reticulation, underground cabling and mechanical installations.
Working across a 1,137-hectare site, our teams supported delivery of one of Australia's largest renewable energy developments, overcoming complex logistics, changing ground conditions and evolving project requirements while maintaining programme performance.
Key Stats:
485MW solar farm
432,000 solar panels installed
65,409 piles driven
106,500m of trenching completed
268,500m of MV cable installed
1,137 hectare development area
12 Months
Duration
Challenge
Managing logistics and delays to free-issued materials across a large-scale renewable energy project
Varying ground conditions requiring extensive pre-drilling activities across sections of the site
Coordinating multiple contractors and simultaneous operations across active work fronts
Adapting to ongoing design changes, evolving project requirements and scope growth during delivery
Maintaining productivity despite civil handover delays, material quality challenges and changing construction priorities
Responding to a significant programme risk when the initially planned mechanical installation contractor was unable to proceed
Solution
Maintained close collaboration with Acciona, suppliers and contractors to coordinate delivery activities and minimise disruption
Re-sequenced installation activities and work fronts to mitigate material delays and maintain programme momentum
Utilised specialist plant, equipment and in-house maintenance capabilities to manage challenging ground conditions and support productivity
Implemented robust QA/QC processes, inspections and reporting procedures to maintain installation quality and traceability
Rapidly mobilised a large mechanical installation workforce and specialist equipment when the planned installation contractor was unable to proceed, maintaining programme certainty and avoiding delays
Maintained strong coordination between civil, electrical and mechanical teams to maximise efficiency across the site
Outcome
Successfully adapted to changing project requirements and contractor interfaces while maintaining delivery momentum
Construction activities completed despite material delays, evolving designs and challenging site conditions
Achieved strong productivity across multiple work fronts through effective planning and coordination
Demonstrated the strength of OCU Group (ANZ)'s integrated delivery capability, with teams collaborating across piling, mechanical, civil and electrical scopes to support successful project delivery
Maintained high standards of quality, safety and programme performance across civil, electrical and mechanical scopes
Demonstrated the capability of our teams to deliver large-scale renewable energy infrastructure within a complex construction environment

